Kuwait City: The Mutla Housing Project in Kuwait is nearing completion. 6 residential projects are being completed. The construction work of the Mutla project is being undertaken by a Chinese company. According to the agreement, the construction of the residential city is expected to be completed by December 2019. However, construction was delayed due to Covid and the contract was extended. The N6 and N9 projects are 85 per cent complete, the N7 and N8 projects 66 per cent, the N10 73 per cent and the N11 project 64 per cent complete.